 
                            Electrical and water meter installation in progress
1 March 2024
 
                            Final touch-up work at Level 8 is currently in progress
1 January 2024
 
                            Landscaping Level 8: Planting and hardscape works in progress
1 December 2023
 
                            Now in progress 2nd tier facade level 30
1 October 2023
 
                            Tower in progress casting slab level 26
1 September 2023
 
                            Tower in progress casting slab level 26
1 August 2023
 
                            Tower in progress casting slab level 23
1 July 2023
 
                            Tower in progress casting slab level 19
1 June 2023
 
                            Tower in progress casting Level 15
19 May 2023
 
                            Overall view. Formwork at Level 12 in progress.
1 April 2023
 
                            Casting SLAB Level 10 in progress
1 March 2023
 
                            In progress casting slab for Level 9
1 February 2023
 
                            Level 9 in progress
1 January 2023
 
                            In progress casting slab level 8
1 December 2022
 
                            Park Homes in progress casting floor slab for level 4
1 November 2022
 
                            Car park in progress concreting at level 6 and ParkHomes at level 4
1 October 2022
 
                            Carpark - level 6 works in progress
1 September 2022
 
                            Level 4 parking slab & Parkhomes level 2 shear wall in progress
1 August 2022
 
                            2nd Floor Slab in Progress
1 June 2022
 
                            1st Floor Structure in Progress
2 March 2022
 
                            Pile Cap Casted 100%
25 Nov 2021
 
                            Underground work in progress
27 Oct 2021
 
                            Commencement of 
18 May 2021
 
                            Piling work in progress
5 April 2021