Site Progress

  • Electrical and water meter installation in progress

    1 March 2024

  • Final touch-up work at Level 8 is currently in progress

    1 January 2024

  • Landscaping Level 8: Planting and hardscape works in progress

    1 December 2023

  • Now in progress 2nd tier facade level 30

    1 October 2023

  • Tower in progress casting slab level 26

    1 September 2023

  • Tower in progress casting slab level 26

    1 August 2023

  • Tower in progress casting slab level 23

    1 July 2023

  • Tower in progress casting slab level 19

    1 June 2023

  • Tower in progress casting Level 15

    19 May 2023

  • Overall view. Formwork at Level 12 in progress.

    1 April 2023

  • Casting SLAB Level 10 in progress

    1 March 2023

  • In progress casting slab for Level 9

    1 February 2023

  • Level 9 in progress

    1 January 2023

  • In progress casting slab level 8

    1 December 2022

  • Park Homes in progress casting floor slab for level 4

    1 November 2022

  • Car park in progress concreting at level 6 and ParkHomes at level 4

    1 October 2022

  • Carpark - level 6 works in progress

    1 September 2022

  • Level 4 parking slab & Parkhomes level 2 shear wall in progress

    1 August 2022

  • 2nd Floor Slab in Progress

    1 June 2022

  • 1st Floor Structure in Progress

    2 March 2022

  • Pile Cap Casted 100%

    25 Nov 2021

  • Underground work in progress

    27 Oct 2021

  • Commencement of superstructure work

    18 May 2021

  • Piling work in progress

    5 April 2021