Air Hitam Entrepreneurs'

Site Progress

  • Mitraland

    1 November 2024: Architectural work in progress.

  • Mitraland

    1 June 2024: Main building works in progress.

  • Mitraland

    1 January 2024: Surcharge removal in progress.

  • Mitraland

    1 December 2023: Surcharge consolidation resting period.

  • Mitraland

    1 November 2023: Surcharge consolidation & Piling work.

  • Mitraland

    1 September 2023: Earthworks and ground treatment works.

  • Mitraland

    1 August 2023: Earthwork & ground treatment works in progress.

  • Mitraland

    30 June 2023: Earthwork & ground treatment works in progress.

  • Mitraland

    1 May 2023: Earthwork & ground treatment works in progress.

  • Mitraland

    1 April 2023: Platform filling works in progress.